HomeMy WebLinkAboutResolution 033-2014 Resolution No. 33-14
A Resolution authorizing Change Order No. 1 for Dakota Nature Park Amenities, Phase VI;
Clark Drew Construction, Inc.
Be It Resolved by the City Council that the following Change Order be allowed for Dakota
Nature Park Trail Amenities, Phase VI:
Construction Change Order No. 1.
Clark Drew Construction via Bowes Construction
Labor/Excavator/Re-Grading=$1,000.00
Subtotal: $1,000.00
Bonding 1%_$10.00
SD Excise Tax @ 2%_$20.00
O/P@8°o=$82.00
Lump Sum Total = $1,112.00
There will be a total addition of$1,112.00
Contract history:
$357,250.00 original contract sum
$0.00 added from previous change orders
$358,362.00 new contract amount after Change Order No. 1
Passed and approved this 22"d day of April, 2014.