HomeMy WebLinkAboutResolution 143-2013 Resolution No. 143-13
A Resolution Authorizing Change Order No. 2A(CCO#2A)for
Brookings Runway Re-Alignment Project(Phase IA)
AIP#3-46-0005-025-2012
Be It Resolved by the City Council that the following change order be allowed for Brookings
Runway Re-Alignment Project (Phase IA), AIP#3-46-0005-025-2012, Construction Change Order
Number 2A:
Additional work to install 18" PVC storm sewer, flared ends and controlled density fill
and adjust bid quantities to as-build quantities for a total decrease of$244.75 to the
current contract price. Increase contract completion date by 45 calendar days.
Passed and approved this 26th day of November, 2013 upon FAA and SDDENR concurrence.
CITY OF BROOKINGS
Tim Reed, Mayor