HomeMy WebLinkAboutResolution 135-2013 Resolution No. 135-13
A Resolution Authorizing Change Order No. 3 for
Dakota Nature Park Phase V, Paving; Bowes Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for Dakota Nature
Park Phase V, Paving:
Construction Change Order No. 3: provide truck hauling of topsoil from City landfill to Dakota
Nature park for edging of newly paved trails, driveways and parking lots.
Bowes Construction, Inc.
Side Dump Truck Hauling =40.25 hrs @$100 per hr. $4,025.00
End Dump Truck Hauling =19.25 hrs @$85 per hr. $1,636.25
Subtotal: $5,661.25
Bonding @ 1%=$56.61
SD Excise Tax @ 2.1%_ $118.89
O/P @ 8%_ $452.90
Lump Sum Total =$6,289.65
There will be a total addition of$6,289.65
Contract history:
$185,300.00 original contract sum
$9,953.45 added from previous change orders
$201,543.10 new contract amount after change order No. 3