HomeMy WebLinkAboutResolution 132-2013 Resolution No. 132-13
A Resolution authorizing Change Order No. 1 for
Dakota Nature Park Phase V, Paving; Clark Drew Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for Dakota Nature
Park Phase V, Paving:
Construction Change Order No. 1: install handicap signage to tie in with existing work. Signage
will be reused, new sono footing, square post sleeve and new upper post will be installed.
Clark Drew Construction, Inc.
Sono tube footing:auger and pour 8 ea @$200 $1,600.00
Sign post material: 1 LS @ $1,288.00 $472.00
Install new posts and reinstall
old signs and discard old post: ea @ $65 $520.00
Remove old footing and discard: 8 ea @$30 $240.00
Subtotal: $2,832.00
Bonding$10 per$1000 = $28.00
SD Excise Tax @ 2% = $57.00
0/P @ 8% =$233.00
Lump Sum Total = $3,150.00
There will be a total addition of$3,150.00.
Contract history:
$209,750.00 original contract sum
$0 added from previous change orders
$212,900.00 new contract amount after change order No. 1
Passed and approved this 26th day of November, 2013.