HomeMy WebLinkAboutResolution 129-2013 Resolution No. 129-13
A Resolution Authorizing Change Order No. 1 for
Dakota Nature Park Trail Paving, Phase V; Bowes Construction, Inc.
Be It Resolved by the City Council that the following Change Order be allowed for Dakota
Nature Park Trail Paving, Phase V:
Bowes Construction
Materials: 61.5 tons of boulders @ $106/ton =$6,519.00
Hauling: 8 hours @ $100/hr= $800.00
Mini-Excavator: 8 hours @ $80/hr. = $640.00
Telehandler: 8 hours @ $125/hr. = $1,000.00
Subtotal: $8,959.00
0/P @ 8%= $716.72
SD Excise Tax @ 2.1% _ $188.14
Bonding 1% =$89.59
Lump Sum Total = $9,953.45
There will be a total addition of$9,953.45
Contract history:
$185,300.00 original contract sum
$0.00 added from previous change orders
$195,253.45 new contract amount after change order No.4
Passed and approved this 26th day of November, 2013.