HomeMy WebLinkAboutResolution 120-2013 Resolution No. 120-13
A Resolution authorizing Change Order No. 1 for the
Bob Sheldon Field Restrooms/Concession Building; Rangel Construction Company, Inc.
Be It Resolved by the City Council that the following change order be allowed for Resolution No. 120-
13 Bob Sheldon Field Restrooms/Concession Building: Construction Change Order No. 1: Rangel
Construction Company, Inc.
Labor and materials for excavation and hauling of additional debris from the foundation and
footings in the existing building site.
Labor& Materials:
Concrete Breaker @ $85 x 3.0hrs= $ 255.00
Backhoe @ $85 x 10.0hrs. = $ 850.00
Hauling Truck @ $85 x 10.0hrs. = $ 850.00
Skid Steer @ $65 x 4.0 hrs. = $ 260.00
Front End Loader @ $95 x 3.5hrs. = $ 332.50
$2,547.50
Overhead @ 6% = $ 152.85
Subtotal = $2,700.35
Profit @ 6%= $ 162.02
Subtotal = $2,862.37
Bond @ 2%= $ 57.25
Subtotal = $2,919.62
SD Excise Tax @ 2.1% = $ 61.31
Total =$2,980.93
There will be a total addition of$2,980.93
Contract history:
$172,950.00 original contract sum
$175,930.93 new contract amount after change order No. 1.
Passed and approved this 22nd day of October, 2013.