HomeMy WebLinkAboutResolution 095-2013 Resolution No.95-13 A Resolution authorizing Change Order No. 4(CCO#4)for Brookings Runway Re-Alignment Project (Phase I) AIP#3-46-0005-025-2012 Be It Resolved by the City Council that the following change order be allowed for Brookings Runway Re-Alignment Project (Phase I), AIP#3-46-0005-025-2012, Construction Change Order Number 4: Increase the contract by$43,146.94 to adjust various bid item quantities to as-constructed quantities and additional work for hard-wiring the closing crosses for Runway 17/35 and Geogrid to allow bridging of an extremely wet and unstable area under the new runway that was an unforeseen condition. Extend the contract substantial completion date by 15 calendar days for the Bid Schedule "B" portion of the project and August 31, 2013 will be the substantial and final completion date for all work in Schedule "B". Passed and approved this 27th day of August, 2013 upon FAA, SDDOT and SDDENR concurrence. CITY OF BROOKINGS /rle-Pt't Tim Reed, Mayor i m i ;Q i °K2c-"2 77.2 Shari hornes, City Clerk