HomeMy WebLinkAboutResolution 076-2008 Resolution No. 76-08
A Resolution Authorizing Change Order#5 (CCO#5) For
2008-03STI Downtown Streetscape Project
Winter Brothers Underground, Inc., Sioux Falls, South Dakota
BE IT RESOLVED by the City Council that the following change order be
allowed for 2008-03SSI,Downtown Streetscape Project:
Construction Change Order Number 5:
Adjust estimated the bid contract for the additional work of removing the steam tunnel and
all asbestos containing material to an estimated depth of 2.5 to 3.5 feet below the final road
grade. The contractor will not be charged tipping fee. This work is on Main Avenue
between 5th Street and the south end of the project, or steam line,which ever comes first.
The removal work will be measured and paid for at a cost of$99 per lineal foot for an
estimated length of 1000 feet for a total change order increase to the contract of$99,000.
Extend the contract date by 15 calendar days for the preceding work.
This resolution amends Resolution No. 74-08,passed and approved on the 26th day of
August 2008.
CITY OF BROOKINGS
Scott unsterman,Mayor
p�TYOF.",
1
cr
ornes, City Cler