HomeMy WebLinkAboutResolution 063-2008 Resolution No. 63-08
A Resolution Authorizing Change Order (CCO#1 FINAL) for 2008 Edgebrook Golf Course
Cart Path and Moriarty Park Sidewalk/Bike Path Project, Contracted Dated September 4,
2007 to Howry Construction Company, Rockwell City, Iowa.
Original Contract Bid Price
Schedule 1. EdgeBrook Golf Course Cart Path
• Bid—2,500 lineal feet @$14.76 LF =$36,900.00
• Actual—measured lineal feet,
3088 LF @ $14.76 LF = $45,578.88
Additional $ 8,678.88
Schedule 2. Moriarty Park Sidewalk/Bike Path
• Bid— 1,800 lineal feet @$14.76 = $26,568.00
• Actual—measured lineal feet,
2,045.3 LF @$14,76 LF = $30,188.63
Additional $ 3,620.63
Total Original Contract Bid Price (Schedule 1 &2) $63,468.00
Total Final Contract Price (Schedule 1 &2) $75,766.71
Additional to Contract $12,298.71
BE IT RESOLVED by the City Council that the following Change Order be allowed for 2008 Cart
Path and Sidewalk/Bike Path Construction:
CCO Number 1 (Final) —Adjust contract with an increase of$12,298.71
Passed and approved this 22nd day of July, 2008.