HomeMy WebLinkAboutResolution 140-2009 Resolution No. 140-09 A Resolution Authorizing Final Change Order (CCO#I Final) for 2009-03STI Willow Springs Circle Street Improvement Project Bowes Construction Inc., Brookings, SD Be It Resolved by the City Council that the following change order be allowed for 2009- 03STI Willow Springs Circle Street Improvement Project: Construction Change Order Number I Final: Add 8" PCC Valley Gutter and Fillet for an increase of$1,772.37 to the contract. Adjust estimated bid quantities to actual "as build" quantities for a total decrease of$2,230.00. Adjust contract completion date to November 2, 2009 and charge the contractor one day of liquidated damages for November 3, 2009 in the amount of$300.00. Passed and approved this 15th day of December, 2009. CITY OF BROOKINGS Tim Reed, Mayor _�9, cirr �:>......... o_ 'y 1?/Aiittfej ‘)i':71;Ir //2a ( ari Thornes, City Clerk