HomeMy WebLinkAboutResolution 140-2009 Resolution No. 140-09
A Resolution Authorizing Final Change Order (CCO#I Final) for
2009-03STI Willow Springs Circle Street Improvement Project
Bowes Construction Inc., Brookings, SD
Be It Resolved by the City Council that the following change order be allowed for 2009-
03STI Willow Springs Circle Street Improvement Project:
Construction Change Order Number I Final:
Add 8" PCC Valley Gutter and Fillet for an increase of$1,772.37 to the
contract.
Adjust estimated bid quantities to actual "as build" quantities for a total decrease
of$2,230.00.
Adjust contract completion date to November 2, 2009 and charge the
contractor one day of liquidated damages for November 3, 2009 in the amount
of$300.00.
Passed and approved this 15th day of December, 2009.