HomeMy WebLinkAboutResolution 128-2009 Resolution No. 128-09
A Resolution Authorizing Change Orders 1 thru 4 (Final)For
Larson Ice Center Red Rink Project
Beck& Hofer Construction
BE IT RESOLVED by the City Council that the following change orders be allowed for the
Larson Ice Center Red Rink Project:
Change Order Number 1 —Extend hot water line to existing mixing valve for an
increase of$1,552.03
Change Order Number 2—Walkway bridge revision for an increase of$3,366.50
Change Order Number 3 —Changes to plastic laminate lockers for an increase of
$4,131.92
Change Order Number 4—Repair concrete floor at exterior doorway (increase
$1,632.78), connect radiant tube heat to building controls (increase
$2,699.81), light fixture revision ($ 0 change), replace lockers with in-
stock lockers (decrease $2,881.64) for a total increase of$1,450.95
Adjust total contract amount(CO 1 thru 4)by an increase of$10,501.40 and close out
the project.
Adjust contract final completion date to September 21, 2009.
Passed and approved this 8th day of December, 2009.