HomeMy WebLinkAboutResolution 002-2009 Resolution No. 02-09
A Resolution Authorizing Final Change Order (CCO#1 Final) For
Airport Miscellaneous Electrical Improvement Project
AIP#3-46-0005-019-2006
Brookings Electric Construction, Inc., Bushnell, SD
BE IT RESOLVED by the City Council that the following change order be allowed for
Airport Miscellaneous Electrical Improvement Project AIP# 3-46-0005-019-2006:
Construction Change Order Number 1 Final (CCO#1 Final):
Adjust contract price for the work to remove&dispose of extra depth pavement at inset
lights and for constant brightness modifications to supplemental wind cone for a total
increase of$5,145.52 to final out the project.
Adjust completion date by 213 calendar days.
Passed and approved this 13th day of January,2009.