HomeMy WebLinkAboutResolution 082-2013 Resolution No.82-13 A Resolution authorizing Change Order No. 1 (CCO#1 Final)for 2012-01SWR Concrete Maintenance Project; Concrete Contractors, Inc. Be It Resolved by the City Council that the following change order be allowed for 2012-01SWR Concrete Maintenance Project: Construction Change Order Number 1 (Final) Adjust plan quantities to as-built quantities for a total decrease of$22,740.18 to close out the project. Adjust contract completion date by 17 working days to close out the project, which will result in liquidated damages of 25 working days at $50.00 per day being charged to the contract. Passed and approved this 13th day of August, 2013. CITY OF BROOKINGS ateAl Tim Reed, Mayor A ,Y , Cr .. OF'ornes, City Clerk