A Resolution authorizing Change Order No. 1 (CCO#1 Final)for
2012-01SWR Concrete Maintenance Project; Concrete Contractors, Inc.
Be It Resolved by the City Council that the following change order be allowed for 2012-01SWR
Concrete Maintenance Project:
Construction Change Order Number 1 (Final)
Adjust plan quantities to as-built quantities for a total decrease of$22,740.18 to close
out the project.
Adjust contract completion date by 17 working days to close out the project, which will
result in liquidated damages of 25 working days at $50.00 per day being charged to the
contract.