HomeMy WebLinkAboutResolution 114-2010 Resolution No. 114-10
A Resolution Authorizing Change Order No. I (CCO#I Final) for
2010-03SSI Village Square Drainage Improvement Project
T&R Contracting, Inc.
Be It Resolved by the City Council that the following change order be allowed for 2010-03SSI
Village Square Drainage Improvement Project:
Construction Change Order Number I (Final):
Adjust contract cost to modify a sewer service from a 6" to an 8" service for an increase of
$1,355.41, add ballast rock under the valley gutter due to unstable and saturated subgrade for
an increase of$8,596.48, add retaining walls around two trees to reduce erosion for an
increase of$1,868.75, add grading and soil preparation in a low area of the project for an
increase of$155.25, add lawn seeding on the SDSU property that was disturbed by
construction access for an increase of$575.00, and adjust plan quantities to as-built quantities
for a total increase of$13,697.57 to the contract.
Passed and approved this 28th day of December, 2010.
CITY OF BROOKINGS
Tim Reed, Mayor
•
%
e J
• .14
.�! 1 -6 4
Shari hornes, City Clerk