HomeMy WebLinkAboutResolution 105-2010 Resolution No. 105-10
A Resolution Authorizing Final Change Order (CCO#I) For
Landfill Trench 4 East
R. L. Larson Excavating, Inc.
Be It Resolved by the City Council that the following change order be allowed for Landfill
Trench 4 East:
Final Construction Change Order Number I:
Description:
1)Zone A material specification adjusted to 90-100 passing 3/8 sieve. Change in contract $ -0-
2)Extra backhoe work to tie in clay liner from 3 east to 4 east. Change in contract add $ 12,500.00
3)Add cleanout to North-South Leachate Line. Change in contract add $ 4,000.00
4)Add extra insulation between leachate pipe and culvert. Change in contract add $ 3,500.00
5)Install additional 650 feet of 12 foot fence. Change in contract add $ 8,400.00
6)Mass excavation quantity 424,013 to 403,121 cy.=20,892 x$1.40/cy Change in contract deduct ($ 29,249.00)
Net Change Order deduct ($849.00)
Original Contract Amount was $1,130,000.00
Contract price incorporating this change order is $1,129,151.00
Passed and approved this 14th day of December 2010.