Loading...
HomeMy WebLinkAboutResolution 006-2010 Resolution No. 06-10 A Resolution Authorizing Change Order No. I (CCO#I Final) For Brookings Roof Replacement Project BHI Construction, Inc. Be It Resolved by the City Council that the following change order be allowed for the Brookings Roof Replacement Project: Construction Change Order Number I (Final) Decrease of$741.00 to install standard EPDM membrane instead of reinforced membrane because the specified 45-mil membrane cannot be installed in a ballast roof and Increase of$8,618.40 due to the necessary replacement of wet insulation of 1,008 sq. ft. at $1.90 per square foot for a total increase of$7,877.40 to close out the project. Passed and approved this 12th day of January, 2010. CITY OF BROOKINGS zzt� Tim Reed, Mayor ,. -.ATTEST: 4,r.1 -217 hari Thornes, City Clerk