HomeMy WebLinkAboutOrdinance 26-2007 ORDINANCE NO. 26-07
An Ordinance Requiring Compliance
With State And Federal Aviation Requirements
And Pertaining To Proposed Construction Or Alteration Of Objects That
May Affect Navigable Airspace In The City Of Brookings, South Dakota
BE IT ORDAINED AND ENACTED BY THE COUNCIL OF THE CITY OF
BROOKINGS, STATE OF SOUTH DAKOTA, AS FOLLOWS:
I.
CHAPTER 22, ARTICLE VII. CONSTRUCTION OR ALTERATION OF OBJECTS
THAT MAY AFFECT NAVIGABLE AIRSPACE
Sec. 22-500. South Dakota Aeronautics Commission Application for Location
of Aeronautical Hazard.
(a) Before any person or entity may begin construction or alteration
of any structure within two miles from the nearest boundary of any public
airport, the height of which is over ten feet above the elevation of an airport,
for each five hundred feet of distance from the nearest boundary of the airport
(50:1 slope), they shall first file an application with and obtain the approval of
the South Dakota Aeronautics Commission to enter upon and complete such
construction or alteration. However, no application is needed if the
construction or alteration is within the corporate limits of a municipality and is
adjacent to other structures of a permanent character which are an equal or
greater height than the construction or alteration proposed.
(b) The application referred to in Sec. 22-500(a) may be obtained
from the South Dakota Aeronautics Commission.
Sec. 22-501. Application for construction approval - Sixty days notice
required.
A person shall submit the application provided in Sec. 22-500 to the
South Dakota Aeronautics Commission for approval, as required under SDCL 50-
9-1 or 50-9-7, at least 60 days before the proposed date that construction is to
begin. A copy of the application provided in Sec. 22-500 shall be filed with the
City Engineer at the time of filing with the South Dakota Aeronautics
Commission.
Sec. 22-502. Notice to Federal Aviation Administration ("FAA") and City.
Any person, or agent, who intends to sponsor construction, as described
below, is required to submit to the Federal Aviation Administration, with a
contemporaneous copy to the Brookings City Engineer, FAA Form 7460-1, Notice
of Proposed Construction or Alteration to the Federal Aviation Administration,
in accordance with Advisory Circular No. 70/7460-2K, if the proposed
construction or alteration falls within any of the following categories:
1. Greater than 200 feet in height. The proposed object
would be more than 200 feet above ground level at its
location.
2. Near a Public Use Airport or Heliport.
(a)Airport. The proposed object or alteration would be
within
20,000 feet of the Brookings Regional Airport and the
object would exceed a slope of 100:1 horizontally
(100 feet horizontally for each one (1) foot
vertically) from the nearest point of the nearest
runway.
(b)Heliport. The proposed object would be within 5,000
feet of a heliport and would exceed a 25:1
horizontal slope (25 feet horizontally for each one
(1) foot vertically) from the nearest landing and
takeoff area of that heliport.
3. Highways and Railroads. The proposed object is a traverse
way which would exceed the standards listed in Sec. 22-500
(2)(a) and (b) above, after the height of the object is
adjusted upward as follows:
(a) Private road: 10 feet or the height of the highest
mobile object that would traverse the roadway,
whichever is greater.
(b) Other public roadways: 15 feet.
(c) Interstate Highways: 17 feet.
(d) Railroad: 23 feet.
(e) Waterway or any other thoroughfare not previously
mentioned: an amount equal to the highest mobile
object that would traverse the waterway or
thoroughfare.
4. Objects on a Public Use Airport or Heliport. The proposed
construction or alteration would be located upon an airport
or heliport, regardless of height or location.
5. When Requested by the FAA. The FAA may request Form
7460-1 if available information indicates the proposed
construction or alteration may exceed an obstruction
standard or the proposed construction or alteration may
cause electromagnetic interference to aircraft, particularly
construction associated with an AM, FM, or TV station
including a change in authorized frequency or transmitting
power, may cause transmitted signals to be reflected upon
ground-based or airborne air navigation communications
equipment, or affect instrument procedures. In addition,
notice may be requested when the proposal may affect an
air traffic control procedure, may obstruct air traffic
controllers' line of sight capability, or may affect air traffic
control radar.
Sec. 22-503. Types of structures which require FAA Notification.
Construction or alteration of all structures located within the
areas described in this ordinance are subject to reporting. The following
are examples of structures requiring Form 7460-1 Notice to the FAA.
(a) Proposed construction or alteration of structures such as:
(a) Buildings.
(b)Antenna Towers.
(c) Roadways.
(d) Overhead communications and transmission lines as well
as the height of the supporting structures.
(e)Water towers and the supporting structure.
(b)Construction equipment or other temporary structures such
as:
(a) Cranes.
(b) Derricks.
(c) Stockpiles of equipment.
(d) Earth moving equipment.
Sec. 22-504. When FAA Form 7460-1 must be filed.
FAA Form 7460-1 must be submitted to the FAA:
(a) At least 30 days before the earlier of the following:
(a)The date the proposed construction or alteration is to
begin, or
(b)The date the application for a building permit will be
filed.
(b) On or before the date the application for construction is
filed with the Federal Communications Commission (FCC),
if the proposed structure is subject to FCC licensing
requirements.
(c) Immediately by telephone or other expeditious means to
the nearest FSS, with written notification submitted within
5 days thereafter, if immediate construction or alteration
is required as in cases involving public services, health or
safety.
(d)As early as possible in the planning stage but not less than
30 days before construction will begin.
Sec. 22-505. Where to file FAA Form 7460-1.
(a) Notification of the proposed construction or alteration shall
be made on FAA Form 7460-1, Notice of Proposed
Construction or Alteration. Additional information such as
charts and/or drawings that accurately depict the proposed
construction or alteration shall be included to facilitate the
FAA's analysis of the project.
(b)The completed form shall be mailed to the Manager, Air
Traffic Division, of the regional FAA office having
jurisdiction over the area within which the construction or
alteration will occur, and a copy shall be
contemporaneously filed with the Brookings City Engineer.
II.
Any or all ordinances in conflict herewith are hereby repealed.
FIRST READING: August 28, 2007
SECOND READING: September 11, 2007
PUBLISHED: September 14, 2007
CI • ■OKINGS, SOUTH DAKOTA
try t D. M - terman, Mayor
''of sRO°o
p
1y`\SOU'' ''_
ho-nes, City Clerk