HomeMy WebLinkAboutResolution 081-2013Resolution No. 81 -13
A Resolution Authorizing Change Order No. 3 (CCO #3) for
Brookings Runway Re- Alignment Project (Phase I)
AIP #3 -46- 0005 - 025 -2012
Be It Resolved by the City Council that the following change order be allowed for Brookings
Runway Re- Alignment Project (Phase I), AIP #3 -46- 0005- 025 -2012, Construction Change Order
Number 3: Adjust the completion date of the Bid Schedule "A" portion of the project only, to
November 15, 2013 for substantial completion and November 30, 2013 for completion of all
work.
Passed and approved this 23rd day of July, 2013 upon FAA and SDDENR concurrence.
CITY OF BROOKINGS
Tim Reed, Mayor