HomeMy WebLinkAboutResolution 140-2011Resolution No. 140 -1 1
A Resolution Authorizing Change Order No. I (CCO #I Final) For
201 1 -01 SWR Curb & Gutter and Sidewalk Project
Timmons Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for 201 1 -01 SWR
Curb & Gutter and Sidewalk Project:
Construction Change Order Number 1 (Final)
Adjust contract cost for extra rock needed for stabilization of the valley gutter and a reduction
in the steel rebar for the fire department driveway and adjust plan quantities to as -built
quantities to final out the project for a total increase of $2,817.00 to close out the project.
Adjust contract completion date by 10 working days to close out the project.
Passed and approved this 13`h day of December 201 1.
CITY OF BROOKINGS
hornes, City Clerk
Tim Reed, Mayor