Loading...
HomeMy WebLinkAboutResolution 140-2011Resolution No. 140 -1 1 A Resolution Authorizing Change Order No. I (CCO #I Final) For 201 1 -01 SWR Curb & Gutter and Sidewalk Project Timmons Construction, Inc. Be It Resolved by the City Council that the following change order be allowed for 201 1 -01 SWR Curb & Gutter and Sidewalk Project: Construction Change Order Number 1 (Final) Adjust contract cost for extra rock needed for stabilization of the valley gutter and a reduction in the steel rebar for the fire department driveway and adjust plan quantities to as -built quantities to final out the project for a total increase of $2,817.00 to close out the project. Adjust contract completion date by 10 working days to close out the project. Passed and approved this 13`h day of December 201 1. CITY OF BROOKINGS hornes, City Clerk Tim Reed, Mayor