HomeMy WebLinkAboutResolution 139-2011Resolution No. 139 -1 1
A Resolution Authorizing Change Order No. 1 (CCO #2 Final) for
2010 -01 SWR Curb & Gutter and Sidewalk Project
Owens Enterprises, Inc.
Be It Resolved by the City Council that the following change order be allowed for 2010 -01 SWR
Curb & Gutter and Sidewalk Project:
Construction Change Order Number 2 (Final)
Adjust plan quantities to as -built quantities for a total decrease of $25,269.13 to close out the
project.
Adjust contract completion date by 16 working days to close out the project, which will result
in 28.5 working days at $25 per day being charged to the contract.
Passed and approved this 13`'' day of December 201 1.
CITY OF BROOKINGS
hari Thornes, City Clerk
Tim Reed, Mayor