Loading...
HomeMy WebLinkAboutResolution 139-2011Resolution No. 139 -1 1 A Resolution Authorizing Change Order No. 1 (CCO #2 Final) for 2010 -01 SWR Curb & Gutter and Sidewalk Project Owens Enterprises, Inc. Be It Resolved by the City Council that the following change order be allowed for 2010 -01 SWR Curb & Gutter and Sidewalk Project: Construction Change Order Number 2 (Final) Adjust plan quantities to as -built quantities for a total decrease of $25,269.13 to close out the project. Adjust contract completion date by 16 working days to close out the project, which will result in 28.5 working days at $25 per day being charged to the contract. Passed and approved this 13`'' day of December 201 1. CITY OF BROOKINGS hari Thornes, City Clerk Tim Reed, Mayor