HomeMy WebLinkAboutResolution 102-2011Resolution No. 102 -1 1
A Resolution Authorizing Change Order No. 2 (CCO #2) for
201 1 -07STI Main Avenue and Front Street Project
Bowes Construction Inc.
Be It Resolved by the City Council that the following change order be allowed for 201 1 -07STI
Main Avenue and Front Street Project:
• Construction Change Order Number 2
• Adjust contract cost to install additional conduit for light pole wiring, extra work
for a sanitary sewer manhole cover, and to remove concrete pavement and
concrete duct work for the new Front Street intersection for a total increase
$2,144.00 to the contract.
• Extend the completion date to open Front Street by 7 calendar days.
Passed and approved this 23rd day of August, 201 I.
ari ornes, City Clerk
CITY OF BROOKINGS
Tim Reed, Mayor