A Resolution Authorizing Change Order No. 1 (CCO #I Final) For
Brookings Recreation /Bike Path & Structure Project
POENH(I47) PCN 00C2 and EM 8006(49) PCN OIOA
Be k Resolved by the City Council that the following change order be allowed for
Recreation /Bike Path & Structure Project POENH(147) PCN 00C2 and EM 8006(49) PCN
010A
Construction Change Order Number I (Final):
• Adjust contract cost for additional costs for borrow excavation, 24" RCP, grinding curb,
6" concrete sidewalk, 3" rigid conduit, erosion control blanket and adjust bid quantities
to final as -built quantities for a total decrease of $3,582.82 to the contract.
• Adjust contract completion date by 8.0 working days to close out the project, which will
result in 8.0 working days at $750 per working day being charged to the contract.
Passed and approved this 10`h day of May, 201 I.