HomeMy WebLinkAboutResolution 052-2011Resolution No. 52 -1 1 A Resolution Authorizing Change Order No. 1 (CCO #I Final) For Brookings Recreation /Bike Path & Structure Project POENH(I47) PCN 00C2 and EM 8006(49) PCN OIOA Be k Resolved by the City Council that the following change order be allowed for Recreation /Bike Path & Structure Project POENH(147) PCN 00C2 and EM 8006(49) PCN 010A Construction Change Order Number I (Final): • Adjust contract cost for additional costs for borrow excavation, 24" RCP, grinding curb, 6" concrete sidewalk, 3" rigid conduit, erosion control blanket and adjust bid quantities to final as -built quantities for a total decrease of $3,582.82 to the contract. • Adjust contract completion date by 8.0 working days to close out the project, which will result in 8.0 working days at $750 per working day being charged to the contract. Passed and approved this 10`h day of May, 201 I. hari Thornes, City Clerk CITY OF BROOKINGS Tim Reed, Mayor