Loading...
HomeMy WebLinkAboutResolution 037-2011Resolution No. 37 -1 1 A Resolution Authorizing Change Order No. I (CCO #I Final) for 2010 -08STI Street Maintenance Project Bowes Construction Inc. Be It Resolved by the City Council that the following change order be allowed for 2010 - 08STI Street Maintenance Project: Construction Change Order Number I Adjust contract cost to as -built quantities for a total decrease of $72,482.76 to the contract. Adjust contract completion date by 9 working days to close out the project, which will result in 6.5 working days at $100 per day being charged to the contract. Passed and approved this 22' day of March 2011. ornes, City Clerk CITY OF BROOKINGS Tim Reed, Mayor