HomeMy WebLinkAboutResolution 010-2011Resolution No. 10 -1 1 A Resolution Authorizing Change Order No. 2 (CCO #2 Final) for 2009 -05STI SDSU Innovation Campus Infrastructure — Phase 11 Bowes Construction Inc. Be k Resolved by the City Council that the following change order be allowed for 2009 -05STI SDSU Innovation Campus Infrastructure — Phase 11: Construction Change Order Number 2 (CCO #2 Final) Adjust contract cost for additional costs for plugging four existing wells, adding drain tile near the round -about and additional grading work to breach a dike in the northeast section of the site and adjust bid quantities to as -built quantities for a total decrease of $37,330.86 to the contract. Adjust contract completion date to May 15, 2011. Passed and approved this 25th day of January 201 I. Shari Thornes, City Clerk CITY OF BROOKINGS 14,, 0,2,z4 Tim Reed, Mayor