HomeMy WebLinkAboutResolution 010-2011Resolution No. 10 -1 1
A Resolution Authorizing Change Order No. 2 (CCO #2 Final) for
2009 -05STI SDSU Innovation Campus Infrastructure — Phase 11
Bowes Construction Inc.
Be k Resolved by the City Council that the following change order be allowed for 2009 -05STI
SDSU Innovation Campus Infrastructure — Phase 11:
Construction Change Order Number 2 (CCO #2 Final)
Adjust contract cost for additional costs for plugging four existing wells, adding drain tile
near the round -about and additional grading work to breach a dike in the northeast section of
the site and adjust bid quantities to as -built quantities for a total decrease of $37,330.86 to the
contract.
Adjust contract completion date to May 15, 2011.
Passed and approved this 25th day of January 201 I.
Shari Thornes, City Clerk
CITY OF BROOKINGS
14,, 0,2,z4
Tim Reed, Mayor