HomeMy WebLinkAboutResolution 22-080Resolution 22-080
Resolution Authorizing Change Order No. 1, for
2022-08STI Street Maintenance and Overlay Project; Bowes Construction, Inc.
Be It Resolved by the City Council that the following Change Order be allowed for 2022-
08STI, Street Maintenance and Overlay Project:
Construction Change Order Number 1: Adjust plan quantities to include
additional work. The work being added includes replacing storm -damaged
sidewalks, paving an alley as part of an assessment project and adding a curb to
a new sidewalk ramp on 3rd Street and State Avenue to better tie into the existing
yard. The total price increase in the contract for these changes is $79,410.55.
Passed and approved this 27th day of September, 2022.
CITY O"ROOKAt4GS, SD
Oepkie (7. Niemeyer, M
ATTEST:
'Foster, City Clerk