HomeMy WebLinkAboutResolution 22-075Resolution 22-075
Resolution Authorizing Change Order No. 1 (Final)
For 2022-06STI Chip Seal Project; Topkote, Inc.
Be It Resolved by the City Council that the following Change Order be allowed for 2022-
06STI Chip Seal Project:
Construction Change Order Number 1 (Final):
Adjust plan quantities to as -constructed quantities for a total increase of
$6,859.70 to close out the project.
Passed and approved this 13th day of September, 2022.
o• :���;jli.
. Niemeyer, Mayor
ATTEST:
rqo� 2 . •i;11'y�� �
'F ��•,Bo tar 'Foster, City Clerk
DocuSign Envelope ID: OA733041-9BB4-47AB-9062-CEE5122CD999
Change Orde
Date of Issuance: September 13, 2022 Effective Date: Upon Council approval
Project: 2022-06STI Chip Seal Project owner: City/ Of Brookings owner's Contract No.: 2022-06STI
Contract: Date of Contract: April 19, 2022
Contractor: Topkote, Inc. Architect's Project No..
The Contract Documents are modified as follows upon execution of this Change Order:
Description:
Adjust bid quantities to as -build quantities for a total increase of $6,856.70 to the contract to close out the
project.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: Original Contract X Working days Calendar days
Substantial completion (days or date): Sept. 5, 2022
$397,637.78 Ready for final payment (days or date): Sept. 5, 2022
[Increase] from previously approved Change [Increase] [Decrease] from previously approved Change Orders
Orders No. 0 No.
Substantial completion (days): 0 days
$ 0 Ready for final payment (daysl: 0 days
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial completion (days or date): Sept. 5, 2022
$ 397,637.78 Ready for final payment (days or date): Sept. 5, 2022
Increase of this Change Order: [Increase] of this Change Order:
Substantial completion (days or date): 0 days
6 856.70 Ready for final payment (days or date): 0 days
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial completion (days or date): Sept. 5, 2022
$404,494.48 Ready for final payment (days or date): Sept. 5, 2022
1 OMMENDED:
_' E1ngiKW'(if required)
City Engineer
9/14/2022
Approved by Funding Agency (if
applicable)
-- ACCEPTED -
By: By:
Owner (Authorized Signature)
Title: (!I, � tom- Title:
DateDate
Date:
`` ACCEPTED:
36L J5r6 Kiaut,
Contractor (Authorized Signature)
President
9/14/2022
EJCDC No. C-941 (2002 Edition) Page I of I
Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the
Associated General Contractors of America and the Construction Specifications Institute.