HomeMy WebLinkAboutResolution 059-2013 Resolution No. 59-13
A Resolution Authorizing Change Order No. 1 for
East Fire Station Expansion Addition Construction Project;Sunkota Construction
Be It Resolved by the City Council that the following change order be allowed for Resolution No.
59-13; East Fire Station Addition:
Change Order No. 1:
Sunkota Construction
Flooring change in pantry add $1,074.00
Gas line modification to kitchen add $ 447.00
Modify exterior sheathing deduct$ 992.00
Restroom accessories change deduct$ 190.00
Control joints for meeting room add $1,277.00
Adjust brick allowance no change
Liquidated damages for delays deduct$ 800.00
TOTAL add $ 816.00
Contract history: Original contract: $750,000.00
Change Order#1 $ 816.00
Revised contract $750,816.00
Passed and approved this 28th day of May, 2013.