HomeMy WebLinkAboutResolution 050-2013 Resolution No. 50-13
A Resolution Authorizing Change Order No.4 For
Dakota Nature Park Nature Center-Clark Drew Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for Resolution No.
50-13 Dakota Nature Park Nature Center:
Construction Change Order No. 4
Olson Masonry
Materials: Fieldstone = $788.00
Labor: 6 man hours @ $50/hr= $300.00
O/P: Shipping= $300.00
@ 11% = $111.12
Subtotal: $1,500.00
Clark Drew Construction, Inc.
Subtotal = $1,500.00
0/P @ 6% =$90.00
SD Excise Tax @ 2%=$31.80
Bonding 1.2%= $19.46
Lump Sum Total =$1,641.26
There will be a total addition of$1,641.26.
Contract history:
$1,198,700.00 original contract sum
$5,935.76 added from previous change orders
$1,206,277.02 new contract amount after change order No. 4
Passed and approved this 14th day of May, 2013.
CITY OF BROOKINGS
Tim Reed, Mayor
• EEfft
,3•.;i � m
Shari Thornes, City Clerk