HomeMy WebLinkAboutResolution 029-2013 Resolution No. 29-13
A Resolution Authorizing Change Order No. I (CCO#I) for
Brookings Runway Re-Alignment Project (Phase I); AIP #3-46-0005-025-2012
Be It Resolved by the City Council that the following change order be allowed for
Brookings Runway Re-Alignment Project (Phase I), AIP#3-46-0005-025-2012,
Construction Change Order Number I:
Adjust bid quantities to allow for the construction of 12' wide Non-Aircraft Shoulders
on Runway 11/29 and for furnishing, stockpiling, and placing rip rap in areas that were
inaccessible due to land restrictions in the fall of 2012 for a total increase of
$177,497.39 and extend the contract completion date by 25 working days for the
additional work.
Passed and approved this 26th day of March, 2013 upon FAA and SDDENR concurrence.
CITY OF BROOKINGS
4121
Tim Reed, Mayor