A Resolution Authorizing Change Order No. 3 for Dakota Nature Park- Nature Center;
Clark Drew Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for the Dakota
Nature Park Nature Center: Construction Change Order Number 3.
TE Underground Materials: Pipe, fittings, etc. = $1,225.00
Labor: Boring 1" poly: 11.00/ft. @ 830' = $9,130.00
Subtotal: $10,355.00
Prairie Sons Materials: BFP, Meter, etc. = $476.00
Tax @ 6%= $29.00
Labor: 16 hrs. @ 47.00/h.r=$729.00
Travel: 4hrs. @ $47.00/hr. = $182.00
O/P: Truck exp. @ 7.5% = $68.00
Tools @ 3% =$27.00
Fuel Surcharge/mile @ $.10 = $12.00
@ 8% = $124.00
Bonding @ 1.44% =$24.00
Subtotal: $1,670.00
Clark Drew Construction, Inc. Subtotal = $12,025.00
0/P @ 6% =$721.50
SD Excise Tax @ 2%_$254.93
Bonding 1.2%= $156.02
Lump Sum Total = $13,157.45
There will be a total addition of$13,157.45.
Contract history: $1,198,700.00 original contract sum
$1,191,990.00 after change order No. 1
$1,191,478.31 after change order No. 2
$1,204,635.76 new contract amount after Change Order No. 3