Loading...
HomeMy WebLinkAboutRes. 21-106Resolution 21-106 Resolution Authorizing Change Order No. 1, Final, for Project 2021-08STI Street Maintenance and Overlay Project; Bowes Construction, Inc. Be It Resolved by the City Council that the following change order be allowed for 2021 - 08STI, Street Maintenance and Overlay Project: Construction Change Order Number 1 (Final): Adjust plan quantities to as - constructed quantities for a decrease of $25,209.43 and include additional work for an increase of $90,390.72. Combining these will result in the project cost increasing by $65,181.29. To accommodate the additional work, the substantial completion date shall be extended by 10 working days to close out the project. Passed and approved this 14th day of December, 2021. FIH-1 G. Niemeyer, Mayor 'foster, City Clerk