Resolution Authorizing Change Order No. 1, Final, for Project 2021-08STI
Street Maintenance and Overlay Project; Bowes Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for 2021 -
08STI, Street Maintenance and Overlay Project:
Construction Change Order Number 1 (Final): Adjust plan quantities to as -
constructed quantities for a decrease of $25,209.43 and include additional work
for an increase of $90,390.72. Combining these will result in the project cost
increasing by $65,181.29. To accommodate the additional work, the substantial
completion date shall be extended by 10 working days to close out the project.
Passed and approved this 14th day of December, 2021.
FIH-1
G. Niemeyer, Mayor
'foster, City Clerk