HomeMy WebLinkAboutRes. 19-022Resolution 19-022
A Resolution Authorizing Change Order No. 1 (Final), for
2019-07STI Freight On Board Project; Bowes Construction Inc.
Be It Resolved by the City Council that the following change order be allowed for 2019-
07STI Freight on Board Project:
Construction Change Order Number 1 Final
Adjust estimated bid quantities to "as-built" quantities for a total decrease of
($17,463.49) to close out the project.
Passed and approved this 12th day of February, 2019.
CITY OF BROOKINGS
Keith W. Corbett, Mayor
2016-07STI ASPHALT CONCRETE FREIGHT ON BOARD (FOB)
BOWES CONSTRUCTION INC.: CHANGE ORDER NO.1 FINAL
BOWES CHANGE
ITEM WORK OR MATERIAL UNITS PLAN CONSTRUCTION EXTENSION FINAL FINAL ORDER
NO. QUANTITY BID PRICES QUANTITIES COST COST
2 ASPHALT CONCRETE CLASS E, TYPE 1 & E2 TON 500.0 $27.00 $13,500.00 1030.865 $27,833.36 $14,333.36
3 ASPHALT CONCRETE CLASS G, TYPE 1 TON 20.0 $29.00 $580.00 53.995 $1,565.86 $985.86
4 ASPHALT CONCRETE CLASS G, TYPE 1 or 2 85% QUART. TON 100.0 $31.00 $3,100.00 2.080 $64.48 -$3,035.52
5 ASPHALT CONCRETE CLASS G, TYPE 2 TON 20.0 $29.00 $580.00 0.000 $0.00 -$580.00
6 ASPHALT CEMENT TON 80.0 $425.00 $34,000.00 65.950 $28,028.75 -$5,971.25
7 ASPHALT TACK COAT TON 10.0 $600.00 $6,000.00 4.820 $2,892.00 -$3,108.00
8 ASPHALT CLASS HR TON 500.0 $26.00 $13,000.00 54.305 $1,411.93 -$11,588.07
9 ASPHALT CLASS Q TON 20.0 $425.00 $8,500.00 0.000 $0.00 -$8,500.00
SUBTOTAL $79,260.00 $61,796.37 -$17,463.63