RESOLUTION NO. 28-92
RESOLUTIOH AUTHORIZING CHAHGE ORDER N0. 2
FOR MUNICIPAL AIRPORT PROJECT A. I. P. 3-46-0005-08
BE IT RESOLVED By the City Commission that the following change
order be allowed for the Instrument Landing System Project Ho.
3-46-0005-08. This change order is to upgrade 48 foundations and to
change the remote monitoring system for the ILS. Both changes were
required by FAA.
Wilcox Electric Inc.
Contract + CCO #1 S 1, 011, 633
Add, Change Order No. 2 46. 226
New Contract Price 8 1, 057, 859
Approval of this Change Order is contingent upon concurrence by
SDDOT and FAA.
ssed and approved this 21st day of April, 1992
�gRooK�N
�a C�
c� /�
�9 s ;-� �z `�. :t ) � �
m � '` _
Mayor
/-/,����� �.
,G
Finance Officer � �
Chanqe Order No. Two
State of South Dakota FAA Project No. AIP 3-46-0005-08
Name of Airport Brookings Municipal Airvort Location Brookinqs, South Dakota
Contractor Wilcox Electric, Inc. , 2001 N.E. 46th St. , Ransas Citv, MO 64116
To Richard L. Viets Schedule No. ILS
You are hereby ordered to make the following change in the plans and/or
specifications for the above designated project.
1. Description of change to be made:
Chanqe I - Reconfiguration of Remote Monitoring - Reconfiqure from
commercial 1�IICI format to FAA ARMS format, supply and install
reconfiguration kit.
Chanqe II - Redesign and Installation of Upgraded Foundations -
Desiqn and install forty-eight (48) upgraded foundations. Install
foundations incorporating extra design safety factor requested by
FAA.
2. Reason for ordering change:
Chanqe I - FAA Request - Change requested to facilitate interface
to FAA maintenance processor system.
Change II - FAA Request - Upgrade foundations to incorporate
additional design safety factor beyond that dictated by local soil
conditions .
3. Settlement for the cost of the above change is to be made as follows:
Chanqe I - Increase in Contract value by $28,025.00.
Change II - Increase in Contract value by $18,201.00
4. This Change Order increases the contract time by 30 calendar days.
5. Summary of Costs
Total Contract Value prior to this Change Order: S1,011,633.00
Net increase of this Change Order $ 46.226.00
Revised Total Contract Value $ 1.057,859.00
NOTE: This order is not e fective until signed by the SDDOT and FAA.
� Director,
Agreed to by: Michael Howard Contracts & Pricinct 3
Contractor's Authorized Rep. Title at
Agreed to by:
Sponsor's Authorized Rep. Title Date
Agreed to by:
Aviation Enqineer - Office of Aeronautics Date
Agreed to by:
Airports Engineer, FAA Date
Subject to Available Fundinq