HomeMy WebLinkAboutResolution 51-1995 . � RESOLUTION NO. 51-95 RESOLUTION AUTHORIZING CHANGE ORDER NUMBER FOUR(4) FOR LANDFILL CONTRACT (ROUNDS CONSTRUCTION) BE IT RESOLVED by the City Commission that the following change order be allowed for the Landfill Contract with Rounds Construction for extending the length of the contract until December 31, 1995. Passed and approved this 13th day of June, 1995. � Mayor �� � � 9 �g83 � � •,�s o a,fi - Finance Officer , CHANGE ORDER (Instructions on reverse side) No• 4 PROJECT ..Lat�4�.�.�.��,..CQiI�X.�Gt......... DA'i'E OF ISSUANCE ...Ju�e..S.�..�.99.5....... EFFECTIVE DATE ....Jun�..1�......��95............... OWNER .....City„ of„Brookin9s............................................................................... OWNER's Contract No. . NA ................................... CONTRAC'I'OR .R.oun�is..Ga�.stzuc.t.iQn In�NGINEER .................NA.............................. You are directed to make the foilowing changes in the Contract Documents. Description: Extend existing contract to December 31 , 1995 Reason for Change Order. �o match contract term to Calender year Attachments: (List documents supporting change) Attachment #1 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Ori�nal Contract Price Original Contract T'�m�s � subsrancia�Comp�e6on: S e p t e m b e r 3 0, 19 9 5 � NA Ready for final payment: -� �na� Net changes from previous Change Onders No._to No._ Net change from provious Chat�e Orders No._to No._ $ NA � �n Contract Price prior to this Change OrdQ Contract Times prior to this Chaoge Order . Substantial Completion: S e p t emb e r 3 0, 19 9 5 $ NA Ready for final payme�G d.n or dates Net Increase(decrcace)of this Chan�e Onder Net Inerease(decrease)of this Change Order a Np, 9 2 d.n Contract Price with all approved Chaqe Orders Contract�mes with ail approved Change Onders Subscanual Compleuon:D e c emb e r �1 , 1 9 9 5 $ N A Ready for final payment: 1�a r p m h a r �1 � 1 ���, a.ys«dates RECOMMENDED: APP D: ACCEPTED• � B ���. � �,�i.,a,� By. �y; o�� t�l.� Y� Enpneer(Authorned Si�wtwel Own ( utlanzed ignrture� Co�rraelor( Sipatu .. /' q �,y t �"��°°�. ^�c. , Date: (S� / •� /�� Date: � —" � 7J— I � Date:�i..lV�2� l��C� EJCDC No. 1910-8-B (1990 Edition) Prepared by the Engineers Joint Contrxt Documeats Committee and endorsed by The Associated General Coanactors of America. � CHANGE ORDER INSTRUCTIONS A. GENERAL INFORMATION This document was developed to provide a uniform format for handling contract changes that affect Contract Price or Contract Times.Changes that have been initiated by a Work Change Directive must be incorporated into a subsequent Change Order if they affect Contract Price or Times. Changes that affect Contract Price or Contract Times shoutd be promptly covered by a Change Order. The praciice of accumulating change order items to reduce the administrative burden may lead to unnecessary disputes. If Milestones have been listed any effect of a Change Order thereon should be addressed. For supplemental instructions and minor changes not involving a change in the Contract Price or Contract T'imes, a Field Order may be used. B. COMPLETIlVG TI�CHANGE ORDER FORM En�neer initiates the form, including a description of the changes invoived and attachments based upon documents and proposals submitted by Contractor, or requests from Owner,or both. Once Engineer has completed and si�ed the form, all copies should be sent to Contractor for approval. After approval by Contractor, all copies should be sent to Owner for approval. Engineer should make distribution of executed copies after approval by Owner. If a change only applies to Contract Price or to Contract Times,cross out the part of the tabulation that dces not aPP�Y- i a � ATTACHMENT #t 1 EXTENSION OF LANDFILL CONTRACT This change order aould extend the Landfill contract with Rounds Construction from October 1, 1995 to December 31, 1995. Rounds Construction Inc. would receive any additional tonnage payments based on the operational year ending October 12, 1995. Rounds Construction Inc. Mould receive S 25, 000. 00 per month for the months of October, November and December.