HomeMy WebLinkAboutResolution 54-1995 RESOLUTION NO. 54-95 RESOLUTION AUTHORIZING FINAL CHANGE ORDER(CCO #1 FINAL)FOR PROJECT 94-01 SWR THE 1994 SIDEWALK AND CURB AND GUTTER REPAIR(B &B . CONCRETE BE IT RESOLVED by the City Commission that the following change order be allowed for the Project 94-01 SWR with B & B Concrete for the repair of sidewalk and curb and gutter. Construction Chan�e Order Number 1 Final The final increase for a total of$18,131.23 to adjust final quantity payments to the"as built" amounts. A total of 51.5 working days are added to this contract resulting in no liquidated damages being charged. Passed and approved this 13th day of June, 1995. � Mayor ATTEST: ������ � � \ � Finance Officer