Adjust estimated quantities to "as built" for a total increase of$25,085.74.
Passed and approved this 17`�' day of November, 1998
�%� `
Mayor
��'�'%�.,
h �Vp 0
�j t2
� M�R•9 ;�
m�i �883 :�
��+,.ti h•. ..QQ
,s-, ''
Sc .�° '
Finance Officer
.� -
CHANGE ORDER
Order No. 1
Date: November 11. 1998
Agreement Date:
NAME OF PROJECT: Medarv Avenue South - P3301(03) PCEMS 4062
OWNER: Citv of Brookinas
CONTRACTOR: Halstead's Inc.
The following changes are hereby made to the CONTRACT DOCUMENTS:
JUSTIFICATION: Adjustment of Quantities and Additional Items
Change to CONTRACT PRICE:
Original CONTRACT PRICE: $ 213.682.30
Current CONTRACT PRICE adjusted by previous CHANGE ORDER $ 213.682.30
The CONTRACT PRICE due to this CHANGE ORDER will be (increased) (��) by:
$ 25.085.74
The new CONTRACT PRICE including this CHANGE ORDER will be $ 238.768.04
Change to CONTRACT TIME:
The CONTRACT TIME will be (��) (��) by 0 calendar days.
The date for completion of all work will be November 1. 1998 (Date) . � —
Approvals Required:
To be effective this Order must be approved by the Federal agency if it changes
the scope or objective of the PROJECT, or as may otherwise be required by the
SUPPLEMENTAL GENERAL CONDITIONS.
Requested by:
�
Recommended by: ���er .sdc � s � .
Ordered by:
Accepted by: � '