Loading...
HomeMy WebLinkAboutResolution 82-1998 ., RESOLUTION NO. 82-98 RESOLUTION AUTHORIZING FINAL CHANGE ORDER(CCO#2 FINAL) FOR BIKE TRAIL PROJECT 98-OSPRK (BOWES CONSTRUCTION) BE IT RESOLVED by the City Commission that the following change order be allowed for the Bike Trail Project 98-OSPRK Construction change Order Number 2 (Final) Adjust estimated quantities to "as build"for a total increase of$2,766.83. Passed and approved this 18`h day of August, 1998. � Mayor A - �ni c ����,`��Q91iGif�•.�S �� :;M*a 3 ;� �' �o °o;�'•• ....•�OJ1? -� � 4..ro�' f. / Finance Officer POENH(54) PCEMS 4660 POENH(10) PCEMS 628H 98-05PRK BIKE TRAIL PROJECT CHANGE ORDER#2: JULY 21, 1998 ' BOWES CONSTRUCTION TOTAL FINAL TOTAL CHANGE ITEM WORK OR MATERIAL UNITS PLAN UNIT PLAN INSTALLED FINAL ORDER NO. QUANTITY PRICE COST QUANTITY COST COST 1. UNCLASSIFIED EXCAVATION CU.YD. 1763 3.00 5289.00 1763.00 5289.00 0.00 2. CRUSHED GRAVEL BASE COURSE TON 4700 6.25 29375.00 7126.16 44538.50 15163.50 3. 85-100 PEN ASPHALT CEMENT TON 195 145.00 28275.00 168.52 24435.40 -3839.60 4. ASPHALT CONCRETE CLASS E TYPE 1 TON 1500 21.30 31950.00 1582.84 33714.49 1764.49 5. ASPHALT CONCRETE CLASS G TYPE 2 TON 1500 26.30 39450.00 1277.38 33595.09 -5854.91 6. FURNISH & INSTALL 15" RCP CLASS ill LN.FT. 190 21.10 4009.00 128.00 2700.80 -1308.20 7. FURNISH & INSTALL 15" RCP SAFETY EN EACH 12 385.00 4620.00 8.00 3080.00 -1540.00 8. FURNISH & INSTALL 8' X 25' BRIDGE EACH 2 10730.00 21460.00 2.00 21460.00 0.00 9. INSTALL 4" P.C.C. SIDEWALK SQ.FT. 9000 2.50 22500.00 7949.60 19874.00 -2626.00 10. INSTALL 6" P.C.C. SIDEWALK SQ.FT. 800 3.30 2640.00 763.50 2519.55 -120.45 TOTAL OF BID ITEMS $189,568.00 . $191,206.83 $1,638.83 EXTRA ITEMS: REMOVE CURB & GUTTER LN.FT. 0.00 $ 5.00 0.00 12.00 60.00 60.00 INSTALL CURB & GUTTER LN.FT. 0.00 $ 14.00 0.00 12.00 168.00 168.00 TOPSOIL HAULED IN & PLACED CU.YD. 0.00 $ 3.00 0.00 300.00 900.00 900.00 TOTAL OF EXTRA ITEMS $0.00 $1,128.00 $1,128.00 CHANGE ORDER #2 AMOUNT $189,568.00 $192,334.83 $2,766.83 ,