HomeMy WebLinkAboutResolution 108-1999 RESOLUTION NO. 108-99
RESOLUTION AUTHORIZING FINAL CHANGE ORDER(CCO#1 FINAL)FOR
STREET ASSESSMENT PROJECT 99-OZSTA(BOWES CONSTRUCTION)
BE IT RESOLVED by the City Council that the following change order be allowed for
Street Assessment 99-02STA.
Construction Change Order Number 1 Final
Adjust estimated quantities as"as build" for a total increase of$1,350.53.
Passed and approved this 29�'day of November, 1999.
Mayor
ATTES'F:---�>,�
:�
- _���R.9 t''i
`����$t�'� f<;�-�-n n
City����rk.=�
99-02STA STREET ASSESSMENT PRO]ECT
TERESA AVE, MARTIN BLVD, DAVID COVE
'� � ��� ���CHANGE�:ORD�R,�.#1�(FINAL)������ �` �
r .,�- _ 7._��'`.:"}`.� .�:,�.x.. .s,e,.�...�c,s..,sk ,m . r Sa�,C3 � �s.W,.:`.`a
BOWES CONSTRUCTION: 2 NOV 99
BOWES TOTAL FINAL TOTAL CHANGE
ITEM WORK OR MATERIAL UNITS PLAN BID PLAN INSTALLED FINAL ORDER '�
NO. QUANTITY PRICE COST QUANTITY COST COST �i
1. UNCLASSIFIED EXCAVATION CU.YD. 3824.00 4.00 15296.00 3824.00 15296.00 0.00
2. INSTALL 8" P.C.C. FILLET&VALLEY GUTTER SQ.FT. 860.00 5.80 4988.00 775.61 4498.54 -489.46
3. INSTALL CURB &GUTTER LN.FT. 2700.00 11.30 30510.00 2677.10 30251.23 -258.77
4. CRUSHED GRAVEL BASE COURSE TON 2000.00 5.75 11500.00 2324.40 13365.30 1865.30
S. ASPHALT CONCREfE CLASS E IYPE 1 TON 400.00 25.70 10280.00 450.10 11567.57 1287.57
6. ASPHALT CONCRETE CLASS G TYPE 1 TON 400.00 25.70 10280.00 381.22 9797.35 -482.65
7. ASPHALT CEMENT TON 52.00 160.00 8320.00 49.57 7931.04 -388.96
8. ASPHALT FOR TACK TON 1.00 250.00 250.00 1.47 367.50 117.50
9. PLACE TOPSOIL CU.YD. 1087.00 5.00 5435.00 1087.00 5435.00 0.00
10. AD)UST MANHOLES EACH 4.00 210.00 840.00 4.00 840.00 0.00
11. ADJUST WATER VALVES EACH 3.00 150.00 450.00 1.00 150.00 -300.00
;�� FINAL�CHANGE ORDER ������ `s $98,149.00 $99,499.53 $1,350.53
CHANGE ORDER
(Instructions on reverse side) No. 1
PROJECT .....99.-.Q2S�A........................
DATE OF ISSUANCE ....11/2�,99............... EFFECTIVE DATE ......�,�,�1.�/.9�.........................
OWNER ....C�.ty..o�..Bx�Akiz�.gs................................................................................
OWNER's Contract No. ....................................
CONTRACTOR B.o�es.�Constructinn.. ENGINEER .....��,�y..������e�......................
You are directed to make the following changes in the Contract Documents.
Description: Increase of $1350.53 to final out the project.
Reason for Change Order: Adjust esti.mated quantities to As-Built Quantities
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Conh-act Price Original Contnct Times
98 149. 00 Substantial Completion:
� ► Ready for final payment:
Jay.or Jatcs
Net changes from previous Chanee Orders No.�to No.1 Net change from previous Change Orders No._[o No._
$ O days
Contrac[Price prior to this Change Or�er Contract Times prior to this Change Order
Substantial Completion:
g 98,149.00 Ready for final payment:
dnys or datcs
Net Increase�)of this Change Order Net Increase(decrease)of this Change Order
$ 1350.53
days
Contract Price with all approved Chanee Orders Contract Times with all approved Change Orders
Substantial Completion:
� 99,499.53 Ready for final payment:
davs or dates
RECO MENDED: APPROV ACCE , �
Bv• � By: B . . � , �
En n •r(Aulhoriz• Sign: rel Owner(Awhorized Signawrel Contr�ctor(AW Sign•riurel
Date: / /_�� ^ / ,� Date:��'1 / � �� Date: / r — � � �C��
EJCDC No. 1910-8-B (1990 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America.