RESOLUTION NO. 85-99
RESOLUTION AUTHORIZING FINAL CHANGE ORDER(CCO#1 FINAL)FOR
STREET IlVIPROVEMENT PROJECT 99-06STI, SCHEDULE A(BOWES CONSTRUCTION) ,
BE IT RESOLVED by the City Council that the following change order be allowed for
Street Improvement Project 99-06STI.
Construction Chan e Or r N m r 1 F'
S
de u be inal
Adjust estimated quantities as"as build" for a total decrease of$10,197.00.
Passed and approved this 20th day of September, 1999.
M'd�or
-��•r>,,.
� •� �o�`v'
c�i��'
1{� �F.
.>
��,;� ,,
� ��
�
City Administrator
�
99-06STI STREET MAINTENANCE PROJECT
CHANGE ORDER#1: SCHEDULE A
Bowes Construction AUGUST 31, 1999 BOWES FINAL TOTAL CHANGE
ITEM UNITS PLAN UNIT PLAN INSTALLED FINAL ORDER
NO. WORK OR MATERIAL QUANTITY PRICE COST QUANTITY COST COST
SCHEDULE A: STREET SEALING
1. FURNISH &APPLY CRS-2 TON 220 220.00 48400.00 179.29 39443.80 -8956.20
2. APPLY CITY FURNISHED CRUSHED AGG. TON 2400 2.45 5880.00 2016.00 4939.20 -940.80
SUBTOTAL SCHEDULE A: $54,280.00 $44,383.00 -$9,897.00
DEDUCTION FOR 3 WORKING DAYS ($100/DAY) $0.00 300.00 -$300.00
TOTAL CHANGE ORDER #1 $54,280.00 $44,083.00 -$10,197.00