HomeMy WebLinkAboutResolution 90-2000 RESOLUTION NO. 90-00
RESOLUTION ACCEPTING CHANGE ORDER ONE (1) FOR THE ICE ARENA BID
PACKAGE 2 CONSTRUCTION PROJECT (site utilities-Prunty Construction)
BE IT RESOLVED by the Brookings City Council that the following proposals
be allowed for the Ice Arena Bid Package 2 Construction Project and that the City
Manager be authorized to execute a Construction Change Order incorparating these
proposals:
The following items were added to the Ice Arena project by field directives. Unit prices
include bond and excise tax.
1. Hydrant in the northeast corner was moved to a more accessible position.
Add 23 feet of 6"C900 water main @ $13.09 LF. Total $301.07
2. Add (1) 8"22-1/2 water main bend @ $223.10. Total $223.10
3. Add (1) storm sewer inlet @ $1124.76 to increase drainage on west access
drive. Total $1124.76.
TOTAL $ 1648.93
Dated this 18`h day of December, 2000.
CITY OF BROOK S
�
Ma or
G��Y OF BRo Y
����NCOqPG�,f
��. '2�
Z� Ig83 9
��;;.
C�•.....N•
SOl'TH ,
n
Ci Clerk
�
� BANNER
GON8ULTINO ENGINEEqB fi AqCMITECTB
• BANNER ASSOCIATES,INC.
409 22nd Avenue South•P.O.Box 298
Brookings,South Dakota 57006•0298
December 4� 2�0� FAX:(605)6925714
Mr. Gregg Jongeling, PE
City of Brookings
311 Third Avenue
Brookings, South Dakota 57006
RE: Bid Package No. 2—Site Utilities
Brookings Ice Arena
BAI No. 8195
�ear Gregg:
Please review the following proposal from Prunty Construction for additional utility work
for the Brookings Ice Arena project. We have reviewed the costs and they appear
reasonable.
Relocating the fire hydrant in Item 1 was needed because the fire hydrant would have
been on a steep inslope. We had intended the fire hydrant to be located on the upper flat
area next to the Brookings Riding Club Arena; however, the actual constructed contours
• were different than the plan contours. Locating the fire hydrant on the upper shelf helps '
improve the visibility of the hydrant.
The additional water main fitting in Item 2 was needed to change direction where the
water main was stubbed off 32"d Avenue. The allowable deflection in the pipe was not
great enough to allow the pipe to make the transition in direction.
Item 3 was needed to keep the storm sewer pipe parallel with the side of the ice arena
building and the Multiplex building. Keeping the storm sewer pipe parallel to the
buildings allows other underground utilities entering either building to cross
perpendicular to the pipeline.
If you have any questions or need additional information, please feel free to contact our
office.
Sincerely,
l,� .
Richard L. Salonen, PE
Proj ect Manager
• Enclosure
.
• H. Action on Resolution 90-00, accepting change order one (1) for the Ice Arena Bid
Package Two (site utilities—Prunty Construction). The resolution and explanation are
enclosed for your review. This is an addition of$1,648.93 to the contract for site utilities
for the relocation of a fire hydrant, an additional water ma.in fitting, and an addition of a
storm sewer inlet.
•
•