HomeMy WebLinkAboutResolution 84-2000 RESOLUTION NO. 84-00
RESOLUTION AUTHORIZING FINAL CHANGE ORDER(CCO#1 FINAL) FOR
00-01SWR, SCHEDULE A: (Curb & Gutter and Sidewalk Repair Project.)
BE IT RESOLVED by the City Council that the following change order be allowed for
00-01 SWR: Schedule A.
Construction Change Order Number 1 Final
Adjust estimated quantities as"as build" for a total increase of $8,522.26.
Increase contract time by 17 working days.
Passed and approved this 18th day of December, 2000.
�
�
`\,�Y OF BRO�� ayor
�,����;�o;��
�N
Mq
�' 18839 '�<
:o
ZG�J;•.,•• ...,.OP�
��SO�•ZN
,�/'(�`�
' y Clerk
� �
1
00-01 CURB&GUTTER&SIDEWALK PROJECT
CHANGE ORDER#1(FINAL): December 8,2000
B&B CONCRETE
B&B FINAL TOTAL CHANGE
ITEM WORK OR MATERIAL UNITS PLAN BID PLAN INSTALLED FINAL ORDER
NO. QUANTITY PRICE C05T QUANTITY COST COST
1. REMOVE 4"P.C.C. SQ.FT. 4500 1.10 4950.00 3364.39 3700.83 -1249.17
2. REMOVE CURB&GUTTER LIN.FT. 1300 5.15 6695.00 2161.90 11133.79 4438.79
3. REMOVE 6"P.C.C.SIDEWALK SQ.F7. 300 1.45 435.00 0.00 0.00 -435.00
4. REMOVE P.C.C.VALLEY GUTTER&FILLET SQ.FT. 500 1.45 725.00 301.08 436.57 -288.43
5. INSTALL 4"P.C.C.SIDEWALK SQ.FT. 5500 2.60 14300.00 4555.67 11844.74 -2455.26
6. INSfALL 6"REINFORCED P.C.C. SQ.FT. 200 3.10 620.00 94.10 291.71 -328.29
7. INSTALL 6"P.C.C.SIDEWALK&APPROACH SQ.Ff. 2000 3.10 6200.00 2083.17 6457.83 257.83
8. INSTALL CURB&GUTTER LIN.FT. 1500 14.40 21600.00 1958.70 28205.Z8 6605.28
9. INSTALL 8"P.C.C.VALLEY GUTfER&FILLET SQ.FT. 1000 4.10 4100.00 1880.28 7709.15 3609.15
10. ADJUST WATER CURB STOP EACH 5 80.00 400.00 0.00 0.00 -400.00
11. CONCREfE SAWING LIN.FT. 500 4.15 2075.00 212.66 882.54 -1192.46
12. REMOVE ASPHALT CONCREfE PAVEMEIVT SQ.FT. 1500 0.50 750.00 1219.66 609.83 -140.17
Extra: Adjust Inlet on 22nd Avenue So. HOUR 0 20.00 0.00 5.00 100.00 100.00
CHANGE ORDER#1(FINAL) $62,850.00 $71,372.Z6 $8,522.26
r
� E. Resolution 84-00, authorizing final c6ange order(CCO#1 Final) for 00-01SWR,
Schedule A Curb & Gutter and Sidewalk Repair Project. A worksheet for the above
referenced change order is enclosed. T'his project consisted of replacing curb& gutter,
valley gutters, and curb ramps throughout Brookings, with the majority of sites being
north of 6�' Street. Included with this project are sidewalks that were replaced and will be
assessed to the owners. The total bid cost of$62,850.00. However, final quantities result
in an actual for an actual cost of$71,372.26. The cl�ange order amount is an increase of
$8,522.26, adjusting estimated quantities to as-built quantities. The majority of the
increase was for replacement of severely deteriorated curb& gutter in preparation for the
2001 chip seal and overlay project. We also completed numerous curb ramps north of 6�'
Street, which has been an ongoing objective to comply with the ADA requirement of
having curb ramps at every intersection.
•