HomeMy WebLinkAboutResolution 81-2000 RESOLUTION NO. 81-00
RESOLUTION AUTHORIZING F1NAL CHANGE ORDER(CCO#1 FINAL) FOR
00-06STI, SCHEDULE B, C, D & E, STREET MAINTENANCE PROJECT.
BE IT RESOLVED by the City Council that the following change order be allowed for
00-06STI, Schedule B, C, D & E.
Construction Change Order Number 1 Final
Adjust estimated quantities as "as build" for a total decrease of $102,884.95
Passed and approved this 1 l�'day of December, 2000.
�
,
G\'(Y OFBRo
�� ��INCORpQ•.,o� Mayor
z T,�9�°:�
c,r'• �3 :j Q
•., . ti
C�S�L'TFl OP�O
/
��ty Clerk
• • �
00-06STI STREET MAINTENANCE PROJECT T
CHANGE ORDER#1 (FINAL): November 30,2000
Bowes Construction
BOWES FINAL TOTAL CHANGE
ITEM UNITS PLAN BID PLAN INSTALLED FINAL ORDER
NO. WORK OR MATERIAL QUANTITY PRICE COST QUANTITY COST COST
SCHEDULE B: ASPHALT F.O.B. PLANT
1. TON 1000 20.15 20150.00 132.85 2676.93 -17473.07
2. ASPHALT CONCRETE CLASS E TYPE 1 TON 1000 18.00 18000.00 653.01 11754.18 -6245.82
3. ASPHALT CEMENT TON 130 225.00 29250.00 46.388 10437.37 -18812.63
TOTAL SCHEDULE B: , . , . - , .
SCHEDULE C: PAVEMENT REMOVAL AND REPLACEMENT
1. . . 2.84 3408.00 0.00 0.00 -3408.00
2. UNCLASSIFIED EXCAVATION CU.YD. 400 7.00 2800.00 0.00 0.00 -2800.00
3. CRUSHED GRAVEL BASE COURSE TON 400 7.00 2800.00 0.00 0.00 -2800.00
4. ASPHALT CONCRETE CLASS E TYPE 1 TON 300 24.00 7200.00 0.00 0.00 -7200.00
5. ASPHALT CONCRETE CLASS G TYPE 1 TON 300 29.00 8700.00 0.00 0.00 -8700.00
6. ASPHALT CEMENT TON 40 225.00 9000.00 0.00 0.00 -9000.00
7. ASPHALT TACK COAT TON 5 280.00 1400.00 0.00 0.00 -1400.00
TOTAL SCHEDULE C: , . . - , .
SCHEDULE D: CRUSHED GRAVEL
1. TON 1600 4.50 7200.00 1225.75 5515.88 -1684.12
TOTAL SCHEDULE D: �T,�f6�- , . - , .
SCHEDULE E: OVERLAY SITES
1. SQ.YD. 6000 2.54 15240.00 4877.20 12388.09 -2851.91
2. MOBILIZATION FOR MILLING LUMP 1 2200.00 2200.00 1.00 2200.00 0.00
3. ASPHALT CONCRETE CLASS G TYPE 1 TON 1500 24.95 37425.00 1171.92 29239.40 -8185.60
4. ASPHALT CEMENT TON 100 225.00 22500.00 69.64 15669.00 -6831.00
5. ASPHALT TACK COAT TON 10 280.00 2800.00 5.74 1607.20 -1192.80
6. ADJUST MANHOLE RIMS EACH 20 250.00 5000.00 8.00 2000.00 -3000.00
7. ADJUST WATER VALVE BOXES EACH 15 130.00 1950.00 5.00 650.00 -1300.00
TOTAL SCHEDULE E: , . , . - , .
TOTAL CHANGE ORDER#1 (FINAL) $197,023.00 $94,138.05 -$102,884.95
•
TO: City Manager Mike Williams
City Clerk Shari Dunn
FROM: Assistant City Engineer Jackie Lanning
DATE: December 4, 2000
RE: Change Order #1 (Final) for 00-06STI
Maintenance Project
Please find the attached worksheet for the above referenced change order. This project
is used for annual street maintenance. A brief description is as follows:
Schedule B: Asphalt F.O.B. Plant - asphalt that is picked up by Street Dept.
personnel and used for patching curbs and valley gutters that have been replaced, and
• to level streets before they are chip sealed or overlayed.
Schedule C: Pavement Removal and Replacement - used for large digout areas
when the asphalt and subgrade materials need to be removed to repair failing
pavement.
Schedule D: Crushed Gravel - gravel delivered to the Street Dept. to be used on
alleys.
Schedule E: Overlay Sites - a paved 2-inch asphalt overlay for deteriorating
pavements.
The total plan cost of Schedules B, C, D and E was $197,023.00. The actual cost of the
project was $94,138.05. The change order amount is a reduction of$102,884.95, adjusting
estimated quantities to as-built quantities. Most of the reduction of quantities was in
Schedules B and C, which are used on an as-needed basis throughout the construction
season.
JAL:jal
•