HomeMy WebLinkAboutResolution 54-2000 i
RESOLUTION NO. 54-00
RESOLUTION ACCEPTING REQUESTS FOR PROPOSALS(RFP) FOR THE
MULTIPLEX PHASE II CONSTRUCTION PROJECT.
BE IT RESOLVED by the Brookings City Council that the following proposals
be allowed for the MultiPlex Phase II Construction Project and that the City Manager be
authorized to execute a Construction Change Order incorporating these proposals:
RFP #1 Add venting for plumbing $3,832.00
RFP #2 Remove wet soil oil $5,836.00
Alt. A Add carpeting for Annex $17,500.00
Electric Additional Electrical Service Equip. $9,417.00
RFP # 7 Move six(6) electrical connections
From the wall to the floor $14,671.00
Doors Revise aluminum/glass doors $2,079.00
RFP #6 Delete coat closet(Rm 191A) ($2,058.00) Credit
Dated this 28�' day of August, 2000.
CITY OF BROOKINGS
Mayor
G��v oF.sqo
AT � '���<o•..°�-
q,•.,2
oe M ���N
x, qR
G�'•, 1883 9 ��`c
'P ,.�'f`l-o .
M
UT �I
City Cler
�
� �
.
City Engineer
August 28, 2000
UPDATED BUDGET
FOR MULTIPLEX IMPROVEMENTS
August 28, 2000 �
Bid Package 1 Seating (bid price) $ 286,000.
Bid Package 2 & 3 Annex & Arena Improvements
Base Bid $ 1,845,200.
Accept alternates 1, 2, 3, 5, 6, 7 and B $ 274,500.
Contingency (includes carpet Alt A) $ 63,366.
$ 2,183,066.
Sitework (moved to Ice Arena Budget) $260,500.
Holding Barns (moved to Ice Arena Budget) $480,000.
A/E Fees (limiting amount) $280,000.
Landscaping and Irrigation $ 48,098.
Credit for Concrete Floor (Architect's Decision 9-9-99) ($ -69,505.)
Enlarge Asphalt Parking Lot $142,637.
Equipment/Furnishings 353 784.
TOTAL BUDGET $3,964,580.
(from 3-13-2000) •
USE OF CONTINGENCY
From original budget (3-13-2000) $ 63,366.
Accept Alternate A for carpeting Annex $ 17,500.
Remove wet soil for bleacher footings $ 5,836.
Add venting for plumbing (est.) $ 3,832.
Add 800 amp power supply for concerts
1. Utility transformer $ 2,500.
2. Additional service equipment $ 9,417.
Move six (6) electrical connections
from the wall to the floor (waiting for cost) $14,671
Remodel aluminum/glass doors for reuse $2,079
Parking lot additional cost after bids $2,018.
Delete coat closet (Room 191A) ($2,058.)
REMAINING $ 7,571.
S;\gejlupdated multiplex budget.doc