HomeMy WebLinkAboutJPBMinutes_2011_05_12BROOKINGS CITY/COUNTY
JOINT POWERS BOARD MEETING
Thursday, May 12, 2011
The Joint Powers Board met on Thursday, May 12, 2011 with the following members present: Tim
Reed, John Kubal, Deanna Santema-acting as an alternate for Dennis Falken, and Don Larson-acting as an
alternate for Alan Gregg who were both absent. Also in attendance were Jeff Weldon, Stephanie Ellwein,
and Steve Britzman.
REGULAR BUSINESS
Chairperson Kubal called the meeting to order and a quorum was established.
City Manager Jeff Weldon reviewed the financial report.
Motion by Reed, seconded by Santema to approve the minutes from the March 11, 2011 Joint Powers
Board Meeting. All members voted “aye.” Motion carried.
Project Superintendent Dan Volbert with Bossardt Corporation presented the Construction Manager’s
Report. He said that they’ve been at the project a little over a month and have three-fourths of the
footprint of the building done. Volbert said they plan to pour concrete for footings on the east side and
finish excavating next week. He said forming and dam proofing the exterior walls and masonry work on the
elevator shaft will begin after that and then structural steel will start. Volbert said that they are looking at
issuing the Certificate of Occupancy on May 10, 2012 and move-in can start on May 11, 2012.
Project Manager Tom Ginter with Bossardt Corporation said that they plan to have the building
enclosed by October, and then the rest of the work will be done on the inside during the winter months.
Brent Koch with Cannon, Moss, Brygger Architects presented the Architect’s Report. He said that Bid
Package #2 is out for bids and they have had a couple of addendums come out to clarify some things. He
said that they are also answering questions from contractors, and reviewing shop drawings on items from Bid
Package #1.
The board discussed the change order process. Weldon said that they need a process in place for
solidifying change orders. Commission Assistant Stephanie Ellwein noted that the full commission has to
approve every change order request. Weldon said that he can administratively approve them on the city
side, but he said that there will be a level at which he will want direction before approving things
administratively.
Kubal asked if change orders will come before the city council. Weldon said that he needs to be able
to keep on schedule, but they will show up. Due to the high visibility of project, Reed suggested that he,
Kubal and Weldon meet weekly to review change orders and an emergency city council meeting could
always be called if needed. Weldon said that he also needs the flexibility to give an up or down answer out
in the field to keep things moving forward. He also noted that if there are any unusually large change
orders, they will have some lead time to get those discussed.
City Attorney Steve Britzman reminded the board that they will need to watch the cumulative total
for change orders as the project progresses.
The board discussed their upcoming meeting schedule: Bid Package #2 opening on May 17th, Joint
Powers Board meeting May 20th to approve bids and full board approvals of bids on May 24th. Weldon noted
that it could be possible that Bossardt doesn’t like a particular bid and it would have to be rebid. Ginter
said that there are 18 contracts in Bid Package #2. He said that they may not have the review of all 18
contracts done by the May 20th meeting, but will get the ones that are timely done first. The Joint Powers
Board scheduled a May 31st meeting to approve any bids that are not approved at the May 20th meeting.
Weldon said that they will have a much better idea on what the overall project budget will be once the Bid
Package #2 contracts are approved.
Ginter reviewed the current change orders. Motion by Reed, seconded by Santema to approve the
change orders dated May 11, 2011. All members voted “aye.” Motion carried.
Weldon said that they had just received a certified pay request of $84,000 which the city will pay
and bill the county for their share. He said they will start seeing these payments on upcoming financial
reports.
Reed asked about the amount of money they had allocated for a clock and suggested having some
type of artwork placed on the building instead. He said that they could apply the money budgeted, and
they could also do some community fundraising. Santema agreed that she would like to see some sort of
artwork on the building rather than a clock.
By consensus, the board agreed to have Reed contact artist Dale Lamphere to get estimates for a
sculpture.
Weldon said that City Council member Mike McClemans had asked about a back-up power generator
for the new facility. Weldon noted that they made the decision early on that they would not have a
dedicated back-up generator, but have temporary generators that could be used in an emergency during
power outages.
Utility Operations Manager Paul Melby with Brookings Municipal Utilities reviewed a rate reduction
program for businesses with usage of 50 KW or more and those that have dedicated generators where the
generators are turned on during peak hours of usage saving on electrical costs.
Weldon said that they had decided on portable generators versus a dedicated generator because
there isn’t a communications center or a jail in the new facility that would require an immediate back-up,
and they wanted to be sensitive to the residential area by not having a large generator sitting outside the
building. Reed said that a dedicated generator seems too expensive at this time.
Larson said that a back-up generator is more important than a sculpture and is critical to the overall
function of the building. He said that the time to install one is now, not 10 years from now and then trying
to retrofit everything and find a place for a generator. Weldon said that he was conscious of the costs and
issues with public safety and emergency situations, but he could not bring a cost of a quarter-million dollars
to the boards for a back-up generator. He said that it wouldn’t be a critical emergency if power was out for
a half-hour in this new building.
Reed suggested they look at the cost to install a dedicated generator now versus the cost to retrofit
one in later. Weldon said that this would have to be bid and it would be a change to the contract in Bid
Package #2. Kubal asked if they could look at what could be done now that would allow an easier
introduction of a dedicated generator in the future. Koch said that they’ll need to contact their mechanical
engineers at West Plains. Weldon said that they would see what it would take to do that.
ADJOURNMENT
The next meeting is scheduled for Friday, May 20th at 8:00 a.m. Motion by Reed, seconded by Kubal
to adjourn. All members voted “aye.” Motion carried.
It is the policy of Brookings County, South Dakota, not to discriminate against the Handicapped in
Employment or the Provision of Service. The County of Brookings is responsive to requests for
communication aids and the need to provide appropriate access, and will provide alternative formats and
accessible locations consistent with the Americans with Disabilities Act.
____________________________________
Stacy Steffensen
Deputy Finance Officer
Brookings County Finance Office
Published once at the total approximate cost of _______________.