A Resolution Authorizing Change Order No. 9 for Brookings Runway Re-
Alignment Project (Phase I), AIP #3-46-0005-025-2012;
Loiseau Construction, Inc.
Be It Resolved by the City Council that the following change order be allowed for
Brookings Runway Re-Alignment Project (Phase I), AIP #3-46-0005-025-2012,
Construction Change Order Number 9:
Adjust plan quantities to as-constructed quantities and additional work for additional
seeding for the equalization basins for a total increase of$7,474.15 to the current
contract price.
Adjust contract time by 304 calendar days to extend completion date to June 15, 2015.
Passed and approved this 9th day of December, 2014.