HomeMy WebLinkAboutResolution 063-2014 Resolution No. 63-14 A Resolution authorizing Change Order No. 3 for Dakota Nature Park Trail Amenities, Phase VI; Clark Drew Construction, Inc. Be It Resolved by the City Council that the following Change Order be allowed for Dakota Nature Park Trail Amenities, Phase Vf: Construction Change Order No. 3. Clark Drew Construction This Change Order extends the contractor's substantial completion date from July 1 to July 15 due to extreme weather,which inhibited the substantial completion by the original contract date. There will be a total addition/subtraction of$0.00 Contract history: Original Contract Substantial Completion Date: July 1, 2014 New Contract Substantial Completion Date: July 15, 2014 Original Contract Price: $357,250.00 Monetary Change Orders: $ 2,288.00 Final Contract Price: $359,538.00 Passed and approved this 26th day of August, 2014. CITY OF BROOKINGS . 1�� Tim Reed, Mayor �\��o�eA .T} T: y;•` �`:�T ��; .-� �� o; � °�� W C/f u- G • ��'oaK a�' hornes,City Clerk